NEC3 ECS Compensation Event Toolkit

NEC3 ECS Compensation Event Toolkit

  • Cover & Guidance — clause overview, the 5 lifecycle stages explained
  • Set-Up Page — project, parties, fee percentages (Direct 10%, Subcontracted 5%, People Overhead 50% per cl.41 SCC), Active CE selector
  • CE Register — 16-column master register, sample 10 CEs covering most cl.60.1 triggers, validated dropdown for all 19 cl.60.1 events plus bespoke
  • CE Notice — formal cl.61.3 Subcontractor notice, dynamically pulls active CE from Register
  • CE Quotation — headline quotation aggregating Defined Cost + Risk + Fee
  • Defined Cost Build-Up — full Schedule of Cost Components: People (with 50% overhead per cl.41), Equipment (cl.21-25), Plant & Materials (cl.31-32), Charges (cl.41-44), Manufacture & Fabrication (cl.51-52), Design (cl.61-62), Insurance (cl.71), plus separate Subcontracted Work line for the different fee treatment
  • Time Impact — programme delay + mobilisation + revised completion date
  • Risk Allowance — cl.63.6 with two methods selectable
  • PM Assessment — Contractor's own assessment template under cl.64 with reasons checkboxes
  • Acceptance Letter — formal cl.62.3 acceptance from Contractor
  • Rejection Letter — formal cl.62.3 instruction to revise, with required revisions list
  • EW Linkage — cross-references CEs back to the Early Warnings that foreshadowed them, with pre-emption rate %
  • Dashboard — KPIs, status breakdown, exposure tracking, revised Total of the Prices, bar chart